Tappan Zee Constructors will be doing some nighttime road grooving and grinding operations on the New York State Thruway this week. South Nyack mayor Bonnie Christian says the work, which includes the new bicycle and pedestrian pathway, will be taking place behind walls that dampen the sound…
On the Rockland side of the bridge, work continues on the construction of a new intersection at Hillside Avenue and Route 9W, which will eventually provide access to the Thruway in both directions. The work includes fencing, signage, drainage work, and the dismantling of the old bridge’s foundations.